Phase one is done. Phase two is underway.
The work comes in two stages. First, the City of Tulsa repaired the bridge itself: supports, deck, parapet walls, joints and other structural parts. That started in December 2024, moved onto the deck in February 2026, and was reported complete in October 2026. Barricades have kept visitors off the plaza since February.
Second, Downtown Tulsa Partnership is rebuilding the public space on top of the bridge. It announced the project at its October 2026 annual meeting and broke ground on November 16, 2026, nearly six years after the campaign began. Construction is expected to be complete by the end of 2027. The plaza stays closed in the meantime.
SOURCETulsa Flyer, November 16, 2026: construction underway, completion expected by the end of 2027. View source
A $7 million public-private project
The plaza rebuild costs about $7 million. It is led by Downtown Tulsa Partnership and the City of Tulsa. BOK Financial is the lead donor with $1.75 million, and PSO and the George Kaiser Family Foundation are also partners. The budget sets aside a maintenance fund so future repairs are already paid for, and Downtown Tulsa Partnership will help maintain and program the space once it reopens.
The City paid for the structural bridge repairs separately, mostly through Vision Tulsa and street and bridge maintenance funds.
SOURCEThe Oklahoma Eagle, October 20, 2026. View source
The two defining elements are being preserved
Acoustic walls
The original inner concrete walls and concentric planter rings that create the echo are being kept on purpose. JE Acoustics studied how the site produces the effect and advised on how to protect it. “We're not doing much to the center,” Downtown Tulsa Partnership's Emily Scott said at the groundbreaking.
Artificial Cloud
Robert Haozous's 1991 sculpture stays. Downtown Tulsa Partnership says there are no plans to change it.
A more useful place around the phenomenon
The new design, by MKSK Studios, adds new paths, lighting, landscaping, native plants, green space, seating and public art. The north side of the plaza, from the Center to Archer Street, becomes a tiered lawn with open turf and shade. Oklahoma sandstone seating goes near the corners of the center bridge, and the center median is widened and raised to the level of the rest of the plaza so the walk across is one continuous path. The aim is more than restoring the old surface: the elevated plaza should be easier to reach and understand, and a place people want to stay.
One familiar piece is going. Trace, the lighted brick art installation, has reached the end of its useful life and will be removed. New public art will be chosen with the City of Tulsa Arts Commission and community input.
Illustrative planning motif. For official concept renderings, use the project source below.
SOURCEDowntown Tulsa Partnership leads the above-deck public-space project and publishes official renderings. View source
A message to the future
At the November 16 groundbreaking, Downtown Tulsa Partnership, the Tulsa Authority for Economic Opportunity and Mayor Monroe Nichols sealed a time capsule of short notes from Tulsans: hopes, memories and predictions for the city. It is set to be opened in 30 years, in 2056.
Expected late 2027 means verify before visiting
The schedule has already slipped once. Earlier announcements expected the bridge repairs to finish in late 2025 and the public space to open in fall 2026. In October 2026, Downtown Tulsa Partnership targeted fall 2027; at the November groundbreaking, completion was expected by the end of 2027. Until there is an official opening announcement, this guide will not give a reopening day.
The status at the top of this page is controlled by one data file and carries a verification date. Once that date is more than 45 days old, the development build warns maintainers to re-check it.